Pre-meeting actions

  • Review existing pending, estimated, open, and trouble tickets -- PMs
  • Close all stories for which assets have been completed -- PMs
  • Go over all stories that are committed to the current iteration
  • Clone any story that has not been completed yet, and link the cloned story to the existing one
    • Change the status of the newly cloned story to "Ready for Estimation"

...

  • If a story is still in the "Committed to an iteration" status, change its status to "Estimated" so that it can potentially be committed to the next iteration
  • Write new stories or feasible ideas for the next itertion.

First Meeting:

  • Calculate total points completed for current iteration.
  • Go over any newly created stories and revise them if necessary so that they can be estimated
    • Any story that needs to be estimated for the next iteration needs to be but in the "Ready for Estimation" status
  • Present new stories or ideas for the next iteration.
  •  

Second Meeting:

  • Go over all stories that are in the "Ready for Estimation" status and estimate them
    • If the story description does not have enough information so that it can be estimated, change its status to "Open" (<--?), so that it can be revised. Also add an appropriate comment, why it needs revision
    • After estimating a story, change its status to "Estimated"

...