- (5:21am to 6:00am, UCDavis) QA will verify that the system has been successfully upgraded by doing the following:
- [QA test plan tbd]
- [ ]
- ( 6:01am – 6:15am, rSmart and UCDavis) Team will decide go or roll back.
...
- (6:32 am – 7:00 am) To be determined by rSmart.
- (List the first step in rolling back)
- list other steps
- (6:41 am – 6:50am, UCDavis) QA will log in and verify that the fix has been removed by doing the following:
- (6:51 am – 6:55 am, rSmart) will bring up the application
- #(6:56 am – 6:57am, rSmart) will release application to public
- #(6:58 am – 7:00am, UCDavis) QA/PM will send email notification to our SmartSite community to say the system is back up #
- (6:58 am – 7:00am, UCDavis) Project or Program Manager will change the MOTD.