  1. (5:21am to 6:00am, UCDavis) QA  will verify that the system has been successfully upgraded by doing the following:
    1. QA test plan tbd
    2. [ ]tba
  2. (6:01am – 6:15am, rSmart and UCDavis) Team will decide go or roll back.

...

  1. (6:32 am – 7:00 am)      To be determined by rSmart.
    1. (List the first step in rolling back)
    2. list other steps
  2. (6:41 am – 6:50am, UCDavis) QA will log in and verify that the fix has been removed by doing the following:
    1. to be determined
    2. to be determined
  3. (6:51 am – 6:55 am, rSmart) will bring up the application
  4. (6:56 am – 6:57am, rSmart)  will release application to public
  5. (6:58 am – 7:00am, UCDavis)  QA/PM will send email notification to our SmartSite community to say the system is back up
  6. (6:58 am – 7:00am, UCDavis)   Project or Program Manager will change the MOTD.