Personnel
- QC is Sandra
- DBA is Prabhu
Preparation for Swith Over
- (Prabhu) Verify with sysadmin that patching of hammer is completed
- (Prabhu) Verify with Backup admin/Sysadmin that filesystem backup/snapshot is completed
During maintenance window
S = maintenance window + 30 mins
- (S - 15 min ProjManmgt) Set database marker.
- (S - 10 min Programmer) Put all application servers into maintenance mode and shutdown Sakai on each one
- (S + 5m Prabhu) Backup the full database
Fall-back Procedure (If needed) Time D is the decision time made to fallback
- (D + 0m Sysadmin) Shutdown Sakai on smartsite-prod
- (
- (D + 20m Programmer) Restart sakai on head node
- (D + 25m QC) Verify the database marker is in place
- (D + 40m Programmer) Restart sakai on remaining nodes
- (D + 25m Programmer) Take application servers out of maintenance mode