Personnel
- QC is Sandra
- DBA is Prabhu
Preparation for Swith Over
- (Prabhu) Verify with sysadmin that patching of hammer is completed
- (Prabhu) Verify with Backup admin/Sysadmin that filesystem backup/snapshot is completed
- (Prabhu)
During maintenance window
S = maintenance window + 30 mins
- (S - m ProjManmgt/Prabhu) Make sure database marker is set prior to start of the patching.
- (S - m Prabhu) Make sure all application servers are offline.
- (S + m Prabhu) Backup the full database on hammer.
- (S + m Prabhu) Make sure backup of full database on hammer is complete.
- (S + m Prabhu) Shutdown the standby database on Steele and Primary database on Hammer
- (S + m Prabhu) Inform Backupadmin/Sysadmin to start filesystem backup/snapshot on Hammer and Steele.
- (S + m Prabhu) Make sure filesystem snapshot is complete and Start the standby database on Steele and then Primary database on Hammer.
- (S + m Prabhu)
Fall-back Procedure (If needed) Time D is the decision time made to fallback
- (D + 0m Sysadmin) Shutdown Sakai on smartsite-prod
- (
- (D + 20m Sysadmin) Restart sakai on head node
- (D + 25m QC) Verify the database marker is in place
- (D + 40m Sysadmin) Restart sakai on remaining nodes
- (D + 25m Sysadmin) Take application servers out of maintenance mode