Personnel
- Programmer is James Renfro
- QC is Sandra
- DBA is Prabhu
Preparation for production release
- (Programmer) On local system: copy over sakai, gb2, and properties tags to non-release-candidate version
svn copy https://mware.ucdavis.edu/svn/ucd-sakai/sakai/tags/sakai_2-5-x-prod-024-RC1 https://mware.ucdavis.edu/svn/ucd-sakai/sakai/tags/sakai_2-5-x-prod-024 -m "NOJIRA : Cutting sakai_2-5-x-prod-024 from release candidate 1" svn copy https://source.sakaiproject.org/contrib/gradebook2/tags/1.1.3-rc1 https://source.sakaiproject.org/contrib/gradebook2/tags/1.1.3 -m "NOJIRA : Cutting 1.1.3 from release candidate 1" svn copy https://mware.ucdavis.edu/svn/ucd-sakai/sakai-properties/tags/sakai-properties-2-5-x-prod-024-RC1 https://mware.ucdavis.edu/svn/ucd-sakai/sakai-properties/tags/sakai-properties-2-5-x-prod-024 -m "NOJIRA : Cutting sakai-properties-2-5-x-prod-024 from release candidate 1"
- (Programmer) On sakaiprod1: backup sakai.properties and toolOrder.xml, export new files, checkout tag, build
cd ~/config-staging ./tomcatclean.sh & mv sakai.properties sakai.properties-prod-023 mv toolOrder.xml toolOrder.xml-prod-023 svn export https://mware.ucdavis.edu/svn/ucd-sakai/sakai-properties/tags/sakai-properties-2-5-x-prod-024/sakai.properties svn export https://mware.ucdavis.edu/svn/ucd-sakai/sakai-properties/tags/sakai-properties-2-5-x-prod-024/toolOrder.xml cd ~/src rm -rf sakai_2-5-x-prod-022 & svn co https://mware.ucdavis.edu/svn/ucd-sakai/sakai/tags/sakai_2-5-x-prod-024 > ~/co.log ^Z bg tail -f ~/co.log [wait until tinyurl is checked out] ^C cd sakai_2-5-x-prod-024 patches/scripts/apply_patches.pl all mvn install sakai:deploy -Pwith-jsmath > ~/build.log & tail -f ~/build.log [wait until build successful] ^C
During maintenance window
S = maintenance window + 30 mins
- (S - 10 min Programmer) Put all application servers into maintenance mode and shutdown Sakai on each one
- (S + 0m Programmer) Deploy sakai release tag via setup-sakai-node.sh to sakaiprod1 and restart sakai instance
~/config-staging/stop.sh jps [verify that sakai instance is down] ~/config-staging/setup-sakai-node.sh cd $CATALINA_HOME/logs ~/config-staging/start.sh ; tail -f catalina.out [wait until server has started up successfully]
- (S + 20m QC) Verification
- (S + 30m Programmer) Deploy release tag via setup-sakai-node.sh to sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
- (S + 40m Programmer) Start Sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
- (S + 45m Programmer) Take smartsite-prod out of maintenance modeĀ
- (S + 50m Sandra) Send Release Management email
Fall-back Procedure (If needed) Time D is the decision time made to fallback
- (D + 0m Programmer) Shutdown Sakai on smartsite-prod
- (D + 2m Programmer) Remove sakai.properties from config-staging and rename sakai.properties.023 to sakai.properties
- (D + 4m Programmer) Run mvn sakai:deploy from previous tag directory
- (D + 15m Programmer) Deploy previous tag on head node and all other app servers via setup-sakai-node.sh
- (D + 20m Programmer) Restart sakai on head node
- (D + 25m QC) Verify the database marker is in place
- (D + 40m Programmer) Restart sakai on remaining nodes
- (D + 25m Programmer) Take application servers out of maintenance mode