  1. Training schedule issues
    1. for Steve - none
    2. for Fernando - working on clicker presentation for Friday, 2/25 10:15 so wants to change drop-in schedule on Friday.  Fernando will email Kirk to change the drop-in hours 10:30-12:30.  This gives Fernando enough time.
  1. Remedy or RSN Ticket Status
    1. Remedy tickets - Steve now has 41. High priority new one's first.  Then move to older high priority tickets. 
    2. Work on tasks from SmartSite Support Plan - Create matrix site for enhancements/user requests; and draft canned messages to point users their request. Provide ticket number so they can track it.
  1. Communication Tasks
    1. See Jira Tickets below
    2. Fernando - SS-276; posted comment Fernando will review document and have Kirk post.

Past Action Items:

  1. Continue to clean up Jira tickets.
  2. Posted changes to CMDCOM-11 on 10/14 for Middleware to complete these changes: due from Middleware Feb 2011.
  3. Posted another comment (on 2/22) to Kirk SAK-549 - Kirk to see if this was still planned:  Where is the request for stuID in roster and pictures?

...