QA Testing Communications Process Description
Note |
---|
This is a Draft .... .... basead on August 29, 2006 code migration meeting: Attendees: |
As a trial, we will adopt the following test documentation process:
...
- Once the test has completed, programmers will review all test
results and create JIRA bug tickets as necessary- If a JIRA bug ticket is created, it is directly linked to the
corresponding STT/LTT
- If a JIRA bug ticket is created, it is directly linked to the
- If there are test results that indicate failure and the programmers
haven't created a JIRA bug ticket for it, for some reason, this test
result will be discussed among Code Migration Meeting attendees and a
decision will be made if there is a need to create a JIRA troube/bug
ticket at that time.