Personnel
- Programmer is Thomas Amsler
- QC is Sandra
- DBA is Prabhu
Preparation for production release
...
- (S - 15 min ProjManmgt) Set database marker.
- (S - 10 min Programmer) Put all application servers into maintenance mode and shutdown Sakai on each one
- (S + 5m Prabhu) Backup the full database
- (S + 35m Prabhu) Apply DB scripts (These are both alter table commands)
- (S + 40m Programmer) Deploy sakai release tag via setup-sakai-node.sh to sakaiprod1.
- (S + 45m Programmer) Restart sakaiprod1 sakai instance
- (S + 50m QC) Verification
- ?Verify that the training and support link no longer points to a project site.
- Verify that the new student view of statistics exists.
- (S + 70m Programmer) Deploy release tag via setup-sakai-node.sh to sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
- (S + 80m Programmer) Start Sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
- (S + 85m Programmer) Take smartsite-prod out of maintenance modeĀ
- (S + 90m Sandra) Send Release Management email
...