Preparation for Swith Over
- (Prabhu) Verify with sysadmin that patching of hammer is completedCopy all the cron jobs from Hammer to Steele.
- (Prabhu) Copy all the scripts from Hammer to Steele and edit the necessary parameters.
- (Prabhu) Verify with Backup admin/Sysadmin that filesystem backup/snapshot is completed Verify with sysadmin about firewall rules, processes limits, Kernel parameters, and oracle limits are the same on hammer and steele.
- (Prabhu)
During maintenance window
...
- (S - m ProjManmgt/Prabhu) Make sure database marker is set prior to start of the patching.
- (S - m Prabhu) Verify with sysadmin that patching of hammer is completed
- (S - m Prabhu) Make sure all application servers are offline.
- (S + m Prabhu) Backup the full database on hammer.
- (S + m Prabhu) Make sure backup of full database on hammer is complete.
- (S + m Prabhu) Shutdown the standby database on Steele and Primary database on Hammer
- (S + m Prabhu) Inform Backupadmin/Sysadmin to start filesystem backup/snapshot on Hammer and Steele.
- (S + m Prabhu) Make sure filesystem snapshot is complete and Start the standby database on Steele and then Primary database on Hammer.
- (S + m Prabhu)
...