Implementation Plan for My Campus Messages, October 28, 2008
MyCampusMessages Upgrade Process, version 2
...
- (06:00 Programmers) Shutdown all application servers
- (06:05 Prabhu) Restore two affected tables in Sakai internal production database,
- (06:15 Prabhu) Resume log transfer/log apply process
- (06:15 Programmers) Start nodes and test
- (06:20 Kirk, Sandra, QA,...) Start testing, verify restore is correct
- (06:25 programmer) Adjust iptables
- (07:00) System ready for public access