- (UCDavis programmers) Shut down Davis Smartsite Prod.
- (UCDavis DBA) Send rSmart a final snaphot of SmartSite-PROD internal database.
- (UCDavis SysAdmin) Perform the final rsynch for AFS against the uncontaminated content store.
- (rSmart) Load final database snapshot.
- (rSmart) Perform database conversion.
- (rSmart) Run configuration spreadsheet.
- (rSmart/UCDavis) Complete manual configuration.
User Content Verification Testing
[Pete's content test plan here]
Function Verification Testing
- Bring up the system in maintenance mode
- Verify content was migratedVerify all critical tools are present and functional (open, basic function, close) for project and course sites.
- Test and Quizzes
- Gradebook 2 (Just make sure it's populated)
- Section Info
- Site Info
- Verify that we can create sites.
- Verify that existing course and project sites have their same tools (identify 20 (5 each) of these to verify)
- Verify all known critical and blocker bugs have been fixed
- Verify that OSP is fixed or not available for users.
- Verify Guest Access:
- add a guest,
- register as a guest,
- activate a guest,
- use the forgot your password function.
- Verify that my campus messages works and doesn't require a second login.
- Verify that the Support and Training link is present
- Verify that project sites have the site statistics tool
- Can Lead TAs use it?
- Can Instructors use it?
- Verify that all our tools are present for project and course sites and the defaults are checked.
- Make sure that ad hoc groups works in old project sites.
- Verify final grade submission url is point toward My Prod.
- Verify Davis database markers can be found; internal database converted correctly
- Verify the PDA portal works
- Verify that the performance is 3 sec or better by running a load test.
- Verify that that all our roles exist:
- new course sites can add Lead TA;
- new project sites can add Organizer and Participant.
- Auditor,
- Verify that the names of each server appears including the tag
- Verify the gateway is correct
- Verify that MOTD works correctly
- Verify response time is good
- Verify Phoenix hot spare is being updated
- Verify table create scripts are running as scheduled
- Confirm Melete files exist and we can export a converted module
- Verify SU (Super User) functionality in order to conduct intensive QA testing.
...