Personnel
...
- Programmer is James Renfro
- DBA is Prabhu Pilli
- QC is Sandra
Preparation for production release
- (Programmer) Copy over sakai and properties tags to non-release-candidate version
- svn copy https://mware.ucdavis.edu/svn/ucd-sakai/sakai/tags/sakai_2-5-x-prod-018-RC1 https://mware.ucdavis.edu/svn/ucd-sakai/sakai/tags/sakai_2-5-x-prod-018
- svn copy https://mware.ucdavis.edu/svn/ucd-sakai/sakai-properties/tags/sakai-properties-2-5-x-prod-018-RC1 https://mware.ucdavis.edu/svn/ucd-sakai/sakai-properties/tags/sakai-properties-2-5-x-prod-018
During maintenance window
- (ProjManmgt) Set database marker.
- (S + 0 min Programmer) Put all application servers into maintenance mode and shutdown Sakai on each one
- (S + 2m Programmer) Deploy sakai release tag via setup-sakai-node.sh to sakaiprod1.
- (S + 5m Programmer) Restart sakaiprod1 sakai instance
- (S + 10m QC) Verification
- (S + 30m Programmer) Deploy release tag via setup-sakai-node.sh to sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
- (S + 40m Programmer) Start Sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
- (S + 50m Programmer) Take smartsite-prod out of maintenance modeĀ
- (S + 55m Sandra) Send Release Management email
Fall-back Procedure (If needed) Time D is the decision time made to fallback
- (D + 0m Programmer) Shutdown Sakai on smartsite-prod
- (D + 2m Programmer) Remove sakai.properties from config-staging and rename sakai.properties.017 to sakai.properties
- (D + 5m Programmer) Deploy previous tag on head node and all other app servers via setup-sakai-node.sh
- (D + 15m Programmer) Restart sakai head node after verifying with DBA that restore is complete
- (D + 20m ProjManmgt) check database marker
- (D + 25m Programmer) Restart sakai on remaining nodes
- (D + 30m Programmer) Take application servers out of maintenance mode