Phase Two: Clean up code and port to testing. Remaining code clean up includes error handling and messages. Code changes are documented below under Code Modifications #codemods. Code will be ported to current collab version and current Davis versions for testing in both environments. Fixes will be completed before porting to Sakai collab QA. Success will be measured by proven ability to import a single, Samigo-compliant assessment with all current (as of 8/10/06) question types in multiple test environments. Failure to import successfully will elicit an error message.
Estimated timeline: August 14 - September 8; 4 weeks
Revised delivery due to sick leave and svn setup: August 14 - September 22; 6 weeks Status: In Progress at 90%
Status Update: Code release to Stanford for review on 9/13/06. Awaiting testing and feedback
Local code Status: In Code Review, Assigned to Jon Gorrono Sept. 25
Passed QA 10/25/06: tc-matrix-testsquizzes-qpools_v2-1-x-1_pass.xls
Moved to SmartSite on 10/28/06

Phase Three: Release to collab source code is the final measurement. Major or higher priority fixes reported within 6 months of release are within the scope of this phase.
Estimated release to collab source code: current release estimate is now after the 9/15 sakai v2.3 release

...