During rollout morning:
- (04:30 Database backSandra) Set database markers
- (05:30(05:30 Mike, Joncarlo or somebody04:35 Michael) Shutdown all 7 sakai app servers.
- (0504:32 40 Prabhu) Back up production database so that it can be fully restored.
- Parallel Tasks
- (05:35 Joncarlo) Deploy SAK-24862600 switch
- (05:35 Mike) Run svn update in ucd-help on sakaiprod1
- (05:52 Prabhu) Confirm backup finished
- (05:52 Prabhu) Run DB upgrade scripts on SAK-2451 and SAK-2439
- (05:55 Mike) Deploy Prod Tag 009 (This deploys JIRAs SAK-2238 and SAK-1515) on sakaiprod1
- (06:05 Mike) Start sakaiprod1
- (06:06 Mike) Test simple functions
- (06:10 Mike) If simple test is OK, then start deploying sakaiprod2-6 and sakaiprodmail1
- (06:20 Mike) Start all other app servers(sakaiprod2-6 and sakaiprodmail1)
- (06:22 Mike) Remove maintenance mode for sakaiprod1-6 and sakaiprodmail1
- (06:25 Mike) Validate all app servers are not in maintenance mode
Fall-back Procedure (If needed)
- (06:00 Prabhu) Run the restore
- (06:00 Michael) roll back the executable for all upgrade changes
- (06:40 Michael)
...
- TBDbring up prod1
- (06:43 Sandra and Kirk) QA SmartSite to make sure it's back in its correct state. Check for database markers
- (