Release the system to public
• (6:00am ---to 6:15am, rSmart) bring up all application servers.
• (6:15am ---to 6:20am, rSmart) will release application to public by reapplying normal mode.
• (6:20am --to 6:23am, UCDavis) QA/PM will send email notification to our SmartSite community to say the system is back up. (6:23am --to 6:25am, UCDavis) Project or Program Manager will change the MOTD.
Rollback
• (6:00am ---to 6:45am, rSmart) Restore the internal database.
♣ Deploy prior code tag (2.6.2.10) to all 7 tomcats.
♣ Bring up one node to test .
• (6:45am ---to 6:50am, UCDavis) QA will log in and verify that the fix has been removed by doing the following:
♣ Check database markers.
♣ Check duplicate section issue.
♣ Check gradebook menu and tree configuration.
• (6:50am ---to 7:05am, rSmart) will bring up remaining nodes
• (7:05am ---to 7:10am, rSmart) will release application to public
• (7:10am ---to 7:13am, UCDavis) QA/PM will send email notification to our SmartSite community to say the system is back up
• (7:13am ---to 7:15am, UCDavis) Project or Program Manager will change the MOTD.
...