Phase One: Code review and prototype importing a single xml Samigo-compliant file. Samigo already features the ability to import a QTI-compliant xml file that meets application-specific metatdata. Phase One success parameters include the successful import of a single-section Samigo-compliant assessment.
Timeline: July 24 - August 11; 3 weeks Status: Completed

Phase Two#codemods: Clean up code and port to testing. Remaining code clean up includes error handling and messages. Code changes are documented below under Code Modifications. Code will be ported to current collab version and current Davis versions for testing in both environments. Fixes will be completed before porting to Sakai collab QA. Success will be measured by proven ability to import a single, Samigo-compliant assessment with all current (as of 8/10/06) question types in multiple test environments. Failure to import successfully will elicit an error message.
Estimated timeline: August 14 - September 8; 4 weeks
Revised delivery due to sick leave and svn setup: August 14 - September 22; 6 weeks Status: In Progress at 90%
Status Update: Code release to Stanford for review on 9/13/06. Awaiting testing and feedback

...