VetMed Developers Meeting

...

CERE Integration

Coordinating various processes running/updating to CERE

Keith - wrap Wrapping up current features on CREST

Scott - batch Batch processing for checks against CREST to update schedule data in CERE; consider
Group Discussion: Consider logging and every .5 hrs to determine impact on performance; initial changes more frequent than later methods;
unsure of performance of CRUD during batching - generation of orphans? race conditions? both processes using web services

Scott, Chris, Keith -
Discussion of changes to information sharing btwn between systems
. Data from CREST to CERE does not have the concept of sections
; Scheduling data may differ btwn between course and labs.
Resolution Possible resolution of sessions based on student group?
May have issues with users in multiple 299's; not an imminent problem but needs to be addressed down the road.
Checking for batch run is a field by field comparison - need to verify; Ray will check out new code on my this afternoon;

Decision: Run process every .5 hrs on 15 and 45 after the hour; modify based on logged responses, if needed

EVALS

...

Scott - Phil is almost done w/template generation (authoring);
Taking Status of taking the evaluation and presentation aspects of; Scott now working on taking evaluation portion, but will hand off to Phil; interface ie Scott will shift to working on the interface, i.e., viewing what evals are available now on Scott's plate; . He will coordinate w/Chris for mockups of listing evaluation listings on user's MyWorkspace to linkto or access eval evaluation tool embedded in the course site.

Gradebook

...

Beau asking for patches from IET; no response?SOM - working w/

School of Medicine (SOM)

SOM is working with vanilla Sakai and Ilios; what changes will they need to go for working design?

...