- (S - 10 min Programmer) Put all application servers into maintenance mode and shutdown Sakai on each one
- (S + 0m Programmer) Deploy sakai release tag via setup-sakai-node.sh to sakaiprod1 . and restart sakai instance
(S + 10m Programmer) Restart sakaiprod1 sakai instanceNo Format ~/config-staging/stop.sh jps [verify that sakai instance is down] ~/config-staging/setup-sakai-node.sh cd $CATALINA_HOME/logs ~/config-staging/start.sh ; tail -f catalina.out [wait until server has started up successfully]
- (S + 20m QC) Verification
- (S + 30m Programmer) Deploy release tag via setup-sakai-node.sh to sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
- (S + 40m Programmer) Start Sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
- (S + 45m Programmer) Take smartsite-prod out of maintenance modeĀ
- (S + 50m Sandra) Send Release Management email
...