  • (S - 10 min Programmer) Put all application servers into maintenance mode and shutdown Sakai on each one
  • (S + 0m Programmer) Deploy sakai release tag via setup-sakai-node.sh to sakaiprod1. on sakaiprod1:
    No Format
    
    ~/config-staging/setup-sakai-node.sh
    cd $CATALINA_HOME/logs
    ~/config-staging/start.sh ; tail -f catalina.out
    [wait until server has started up successfully]
    
  • (S + 10m Programmer) Restart sakaiprod1 sakai instance
  • (S + 20m QC) Verification
  • (S + 30m Programmer) Deploy release tag via setup-sakai-node.sh to sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
  • (S + 40m Programmer) Start Sakaiprod2 . . . sakaiprod6, and sakaiprodmail1.
  • (S + 45m Programmer) Take smartsite-prod out of maintenance modeĀ 
  • (S + 50m Sandra) Send Release Management email

...